St. Louis Premium Outlets - Chesterfield, Missouri

This $3,330,000.00 contract based in Blue Valley Chesterfield, Missouri, was completed during an unusually wet spring with bad/wet soil conditions. The strict deadline (prior to Labor Day) forced a very accelerated schedule where Byrne & Jones completed all work in 65 consecutive calendar days. More than once, we had 3 paving crews, 2 rock crews, 1 pipe crew and supervision (30+ Byrne & Jones employees) working at once plus sub Flyer Striping. The proximity to the Chesterfield Levee required an extensive underdrain system to be installed by B&J which required coordination with Monarch Levee District & MSD. Our scope was completed 4 days before Grand Opening allowing time for punch list & final cleaning.

St. Louis Premium Outlets - Chesterfield, Missouri
St. Louis Premium Outlets - Chesterfield, Missouri
St. Louis Premium Outlets - Chesterfield, Missouri
St. Louis Premium Outlets - Chesterfield, Missouri
St. Louis Premium Outlets - Chesterfield, Missouri
St. Louis Premium Outlets - Chesterfield, Missouri
St. Louis Premium Outlets - Chesterfield, Missouri

SCOPE

Asphalt base rock, asphalt paving (conventional, super pave, porous), stabilization fabric, 4 inch pvc under drain, striping, traffic signage.

SPECIFICS

55,000 tons rock
10,000 tons conventional asphalt
7,000 tons superpave asphalt
4,500 ton porous asphalt
35,000 sy rock fabric
20,000 lf 4 inch pvc underdrain

TECHNICAL INFORMATION

GC: Hardin / DPR
Owner: Simon Property Group